Former Vallejo Manufactured Gas Plant Site

5 Documents in Project

Summary

SCH Number
2018102054
Lead Agency
Department of Toxic Substances Control
Document Title
Former Vallejo Manufactured Gas Plant Site
Document Type
NOD - Notice of Determination
Received
Posted
9/15/2022
Document Description
The project involves soil excavation and off-site disposal of impacted soil at permitted disposal facilities, and institutional controls such as land use covenants or deed restrictions. The former Vallejo Manufactured Gas Plant (MGP) is comprised of Operable Unit-1 (OU-1) and Operable Unit-2 (OU-2). On September 12, 2019, the Department of Toxic Substances Control (DTSC) adopted a Negative Declaration in connection with the approval of two Remedial Action Plans (RAPs). The RAPs addressed the remediation of contamination associated with the Former Vallejo Manufactured Gas Plant (MGP) in the City of Vallejo. The site has two Operable Units, OU-1 (26 acres) and OU-2 (0.67 acres), on the south and north sides of Curtola Parkway, respectively. On September 12, 2019, DTSC approved the Initial Study and Negative Declaration (IS/ND) for the RAP and filed a Notice of Determination with the Governor’s Office of Planning & Research, State Clearinghouse. Project activities included remediation plans for OU-1 and OU-2 consisting of excavation and off-site disposal of contaminated soils, and in-place treatment of deeper contaminated soils. The filing documented that the project’s approval would not have a significant effect on the environment and that mitigation measures were not made a condition of project approval. The approved OU-1 RAP called for a combination of excavation and off-site disposal of soils, along with stabilization of soils beneath the groundwater table to achieve cleanup goals. The remedial design and implementation plan for this project indicated that there may be a need to replace the existing storm drain line with new stormwater conveyance routes, however at the time no consideration was made to performing work in the Mare Island Strait. Therefore, this Addendum to the Final IS/ND for the Site is necessary to address the modification to the Project. The updated project activities are consistent with the original activities described in the OU-1 RAP and all work will occur in accordance with both the 2019 RAP and Negative Declaration. No other revisions to the OU-1 RAP are planned.

Contact Information

Name
Sagar Bhatt
Agency Name
Department of Toxic Substances Control
Job Title
Project Manager
Contact Types
Lead/Public Agency

Location

Cities
Vallejo
Counties
Solano
Regions
Citywide, Countywide, San Francisco Bay Area
Cross Streets
Curtola Parkway and Sonoma Boulevard
Zip
94590
State Highways
29, 80, 780
Waterways
Mare Island Strait

Notice of Determination

Approving Agency
Department of Toxic Substances Control
Approving Agency Role
Lead Agency
Approved On
County Clerk
Solano
Final Environmental Document Available at
https://www.envirostor.dtsc.ca.gov/public/profile_report.asp?global_id=60001753 or Department of Toxic Substances Control Site Mitigation and Restoration Program 700 Heinz Avenue Berkeley, CA 94710

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
Yes (Addendum)
(3) Mitigated measures were made a condition of the approval of the project
No
(4) A mitigation reporting or monitoring plan was adopted for this project
No
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
Yes

Attachments

Disclaimer: The Governor’s Office of Planning and Research (OPR) accepts no responsibility for the content or accessibility of these documents. To obtain an attachment in a different format, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613. For more information, please visit OPR’s Accessibility Site.