San Andreas Sanitary District Collection System Improvements Project

2 Documents in Project

Summary

SCH Number
2018092063
Lead Agency
San Andreas Sanitary District
Document Title
San Andreas Sanitary District Collection System Improvements Project
Document Type
NOD - Notice of Determination
Received

Document Description
The project consists of the following: 1) Upsize sewer trunk segments adjacent to San Andreas Creek; 2) Improve maintenance hole geometry at MH E-1200; and 3) Upsize sewers with recurring maintenance issues tributary to the trunk improvements. Project construction is anticipated to take place between 2019-2021. It is anticipated that the project could be constructed between April and October of a single year, and would likely take between 3-6 months, limiting the timeframe of construction to the dry season and avoiding the risks associated with sewer bypassing during wet weather.

Contact Information
Hugh Logan
San Andreas Sanitary District
675 Gold Oak Rd
San Andreas, CA 95249

209-754-3281

Location

Counties
Calaveras
Cross Streets
Treat Ave; California St; Main St; Pixley Ave; High School St; Gold Oak Rd
Zip
95249
Total Acres
~10
State Highways
49
Schools
Calaveras HS
Waterways
San Andrea Creek
Township
4N
Range
12E
Section
17/18/
Base
MD
Other Location Info
San Andreas

Notice of Determination

Approving Agency
San Andreas Sanitary District
Approving Agency Role
Lead Agency
Approved On
Final EIR Available Location
675 Gold Oak Rd., San Andreas, CA 95249

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A Statement of Overriding Considerations was adopted for this project
No
(5) Findings were made pursuant to the provisions of CEQA
Yes