Camp Far West Auxiliary Spillway Expansion Project
4 Documents in Project
Download CSV
New Search
Print
Summary
- SCH Number
- 2018092009
- Lead Agency
- South Sutter Water District
- Document Title
- Camp Far West Auxiliary Spillway Expansion Project
- Document Type
- NOD - Notice of Determination
- Received
- Posted
- 12/6/2018
- Present Land Use
- Yuba County GPD: Public, Z: Resource Preservation and Recreation district
- Document Description
- The Camp Far West Hydroelectric Project (Federal Energy Regulatory Commission [FERC] Project No. 2997) is owned by the South Sutter Water District, and is operated under an existing FERC license. The hydroelectric project is located on the Bear River in Yuba County, CA. Two of the primary features of the hydroelectric project are the Camp Far West Dam and Spillway. SSWD is planning construction of a new auxiliary spillway to meet FERC safety requirements and to accommodate the probable max flood: the Camp Far West Auxiliary Spillway Expansion Project.
- Contact Information
-
Brad Arnold
South Sutter Water District
Lead/Public Agency
2464 Pacific Avenue
Trowbridge, CA 90745
Phone : (530) 656-2242
Location
- Coordinates
- 39°3'11.28"N 121°19'16.84"W
- Cities
- Wheatland
- Counties
- Yuba
- Cross Streets
- Spencerville Rd and Camp Far West Rd
- Zip
- 95692
- Total Acres
- 125
- Parcel #
- 015-370-016-000
- Waterways
- Camp Far West Dam and Reservoir
- Township
- 14
- Range
- 6
- Section
- 21
- Base
- MD
Notice of Determination
- Approving Agency
- South Sutter Water District
- Approving Agency Role
- Lead Agency
- Approved On
- Final Environmental Document Available at
- N/A
Determinations
- (1) The project will have a significant impact on the environment
- No
- (2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
- No
- (2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
- Yes
- (2c) An other document type was prepared for this project pursuant to the provisions of CEQA
- No
- (3) Mitigated measures were made a condition of the approval of the project
- Yes
- (4) A mitigation reporting or monitoring plan was adopted for this project
- N/A
- (5) A Statement of Overriding Considerations was adopted for this project
- No
- (6) Findings were made pursuant to the provisions of CEQA
- Yes
Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613.