10th and O Street Office Building Project

3 Documents in Project

Summary

SCH Number
2018072065
Lead Agency
Department of General Services (DGS)
Document Title
10th and O Street Office Building Project
Document Type
NOD - Notice of Determination
Received
Posted
12/27/2018
Present Land Use
State-owned; occupied by a State-owned paved surface parking lot
Document Description
The project would demolish the existing surface parking and construct a new office building with approx. 488,000 gsf of office space, max. height of 150-feet, occupancy of approx. 2,000 staff, plus limited parking. Project purpose is to consolidate/upgrade regional State office space. It is anticipated that staff occupying the new office building would be legislative staff, staff from other leased space in the region, and/or from one or more other State-owned buildings slated for eventual renovation/upgrade. In addition, state-owned surface parking on the southwest corner of the block bounded by P, Q, 11th, and 12th Streets would be demolished and a new child care facility would be developed to replace an existing child care facility on the southeast corner of the same block.

Contact Information

Name
Stephanie Coleman
Agency Name
Department of General Services
Contact Types
Lead/Public Agency

Location

Cities
Sacramento
Counties
Sacramento
Cross Streets
10th/11th Streets and O St/Neighbors Alley; P, Q, 11th and 12th Streets
Zip
95814
Total Acres
~2
State Highways
50,80,5, 99, 160
Railways
Regional Transit
Schools
Discovery Tree...
Waterways
Sacramento River, American River

Notice of Determination

Approving Agency
DGS
Approving Agency Role
Lead Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
Yes
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
Yes
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
No
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
Yes
(6) Findings were made pursuant to the provisions of CEQA
Yes

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613.

Download CSV New Search Print