State Water Project Water Supply Amendments for Water Management

14 Documents in Project

Summary

SCH Number
2018072033
Lead Agency
California Department of Water Resources (DWR)
Document Title
State Water Project Water Supply Amendments for Water Management
Document Type
NOD - Notice of Determination
Received
Posted
11/6/2020
Document Description
The Department of Water Resources, acting as CEQA lead agency, approved the project on August 25, 2020. The project adds, deletes, and modifies provisions of the Contracts and clarify certain terms of the Contracts that will provide greater water management regarding transfers and exchanges of State Water Project (SMIP) water within the SWP service area. The project does not build new or modify existing SWP facilities nor change any of the Public Water Agencies (PWAs) annual Table A amounts. The project does not change the water supply delivered by the SWP, as SWP water would continue to be delivered to the PWAs consistent with current SWP Water Supply Contract terms and all regulatory requirements.

Contact Information

Name
Peter Thompson
Agency Name
Palmdale Water District
Contact Types
Lead/Public Agency

Name
Agency Name
Palmdale Water District
Contact Types
Project Applicant

Location

Cities
Palmdale
Counties
Los Angeles
Regions
Statewide
Waterways
State Water Project

Notice of Determination

Approving Agency
Palmdale Water District
Approving Agency Role
Responsible Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
Yes
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
Yes
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
No
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
No
(4) A mitigation reporting or monitoring plan was adopted for this project
No
(5) A Statement of Overriding Considerations was adopted for this project
Yes
(6) Findings were made pursuant to the provisions of CEQA
Yes

Attachments

Disclaimer: The Governor’s Office of Planning and Research (OPR) accepts no responsibility for the content or accessibility of these documents. To obtain an attachment in a different format, please contact the lead agency at the contact information listed above. For more information, please visit OPR’s Accessibility Site.