CAL FIRE San Luis Obispo Regional Unit Headquarters Replacement Project
3 Documents in Project
Summary
SCH Number
2018071062
Lead Agency
California Department of Forestry and Fire Protection
(CAL FIRE)
Document Title
CAL FIRE San Luis Obispo Regional Unit Headquarters Replacement Project
Document Type
NOD - Notice of Determination
Received
Posted
10/12/2018
Document Description
The 7.26 acre project site is located at 635 North Santa Rosa St in San Luis Obispo, CA. The CAL FIRE SLO-RUH Replacement project proposes the demolition of approx. 23,000 sf of existing buildings and associated facilities in order to allow for the construction of new site improvements consisting of a max of approx. 39,040 sf of new buildings, including a new admin building, barracks/apparatus building, physical training building, auto shop building, and generator building. The project also proposes new paving for roads and parking, retaining walls, water distribution systems, waste water collection and disposal systems, drainage systems, and erosion control measures. The existing approx. 800 ft. driveway traversing the southern boundary of the project site, is proposed to be widened from its current width of approx. 30 ft. to 40 ft. The driveway would be extended to the west approx. 50 ft. before curving north for an additional 245 ft. and ending at the northern boundary of the site. Additional off-site work will be required at the site entrance from Hwy 1 and within the Caltrans ROW including the driveway approach and installation of multiple emergency beacons. An offsite sanitary sewer manhole would be replaced to the south of the project site.
Contact Information
Name
Pat Kelly
Agency Name
Cal Fire
Contact Types
Lead/Public Agency
Phone
Location
Cities
San Luis Obispo
Counties
San Luis Obispo
Cross Streets
635 North Santa Rosa Street
Zip
93405
Parcel #
073-341-026
State Highways
Hwy 1
Railways
yes
Schools
Cal Poly SLO
Waterways
ephemeral stream
Notice of Determination
Approving Agency
Cal Fire
Approving Agency Role
Lead Agency
Approved On
Determinations
(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
N/A
Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above.