Initial Study Application No. 7384, Director Review and Approval Application No. 4522 and Variance Application No. 4050
2 Documents in Project
Download CSV
New Search
Print
Summary
- SCH Number
- 2018071047
- Lead Agency
- Fresno County
- Document Title
- Initial Study Application No. 7384, Director Review and Approval Application No. 4522 and Variance Application No. 4050
- Document Type
- NOD - Notice of Determination
- Received
- Posted
- 9/25/2018
- Present Land Use
- existing well/single-fam res/rec center
- Document Description
- Construct 500,000-gallon water storage tankw ith boost pumps at the existing well site. Site improvements will be necessary to accomodate the tanks and pumps. The project also proposes to replace water services, install a new 10-inch water mains to replace existing 6-inch and 8-inch mains in selected areas of the District, and to replace all existing water meters throughout the District. A Variance is required to allow the installation of fence and wall in excess of three feet within the front-yard setbacks.
- Contact Information
-
Chrissy Monfette
Fresno County
Lead/Public Agency
2220 Tulare Street, Suite A
Fresno, CA 93721
Phone : (559) 600-4245
Location
- Counties
- Fresno
- Cross Streets
- north side of West F Street, North Third Street
- Parcel #
- 016-265-10ST
- Schools
- Biola-Pershing ES
- Waterways
- Local canals
- Township
- 16S
- Range
- 18R
- Section
- 16
- Base
- DMBM
- Other Location Info
- Biola
Notice of Determination
- Approving Agency
- County of Fresno
- Approving Agency Role
- Lead Agency
- Approved On
- Final Environmental Document Available at
- 2220 Tulare Street, Suite A
Determinations
- (1) The project will have a significant impact on the environment
- No
- (2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
- Yes
- (2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
- No
- (2c) An other document type was prepared for this project pursuant to the provisions of CEQA
- No
- (3) Mitigated measures were made a condition of the approval of the project
- Yes
- (4) A mitigation reporting or monitoring plan was adopted for this project
- N/A
- (5) A Statement of Overriding Considerations was adopted for this project
- No
- (6) Findings were made pursuant to the provisions of CEQA
- N/A
Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613.