IS Application No. 7373 (Michael Oliver, HRBC)

2 Documents in Project

Summary

SCH Number
2018071026
Lead Agency
Fresno County
Document Title
IS Application No. 7373 (Michael Oliver, HRBC)
Document Type
NOD - Notice of Determination
Received
Posted
8/27/2018
Present Land Use
developed/AE-20/AG

Document Description
Allow expansion of an existing cattle slaughtering and meat processing plant on five contiguous parcels in the AE-20 Zone district to include a 33,491 sf, 39.5 ft tall finished goods warehouse distribution center (max of 35 allowed) with truck docks, 54,907 sf processing building, 7,500 sf processing building, employee and truck parking, 180,000 sf anaerobic pond, and a secondary wastewater treatment facility with related improvements on two parcels totaling 59.9 acres; a 13-acre treated wastewater retention basin on a 20-acre parcel; and application of treated wastewater from the facility onto 77.99 and 78.79 acres of farmland.

Contact Information
Ejaz Ahmad
Fresno County
2220 Tulare Street, Suite A
Fresno, CA 93721

Phone : (559) 600-4204

Location

Cities
Kingsburg
Counties
Fresno
Cross Streets
West side of S. McCall Ave between E. Clarkson; E. Elkhorn Ave; 16277 S. McCall Ave
Total Acres
236.68
Parcel #
393-141-06, 08S, 09S, 10S, 13
Township
16S
Range
22E
Section
31
Base
MDBM

Notice of Determination

Approving Agency
County of Fresno
Approving Agency Role
Lead Agency
Approved On
Final Environmental Document Available at
2220 Tulare Street, Suite A, Fresno, CA 93721

Determinations

(1) The project will have a significant impact on the environment
Yes
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
N/A