Vantage Data Centers- Mclaren Data Center Project (City Land Use Permit Number PLN23- 00308, State Clearinghouse #2018062057) - Issuance of ATC-AN-32087

5 Documents in Project

Summary

SCH Number
2018062057
Lead Agency
Santa Clara County
Document Title
Vantage Data Centers- Mclaren Data Center Project (City Land Use Permit Number PLN23- 00308, State Clearinghouse #2018062057) - Issuance of ATC-AN-32087
Document Type
NOD - Notice of Determination
Received
Posted
8/21/2024
Document Description
The Bay Area Air Quality Management District (Air District) has issued an Authority to Construct for the Mclaren Backup Generating Facility (MBGF) for four additional backup diesel generators. The MBGF provides emergency backup power for the Mclaren Data Center (MDC). The MDC consists of three four-story, 175,000-180,000 ft2 data center buildings and a paved parking lot on a 9-acre site. The MBGF consists of 15 to 20 diesel-fired backup generators for each data center building to provide emergency backup power for the buildings' servers in the event of a power outage and also one additional generator for each building to provide emergency power for fire suppression and other life safety systems. The four new diesel-fired backup generators will be for Building CA23. The Air District has already issued Authority to Constructs for SO existing backup diesel engines supporting the three data center buildings. This Authority to Construct authorizes Vantage to install four additional 4043-horsepower emergency backup power generators. These generators will be operated only for emergency purposes, plus up to 37 hours per year for testing, maintenance and reliability purposes. They will not be used for routine data center operations. In addition, the existing permitted generators will have their permit 1/2 conditions changed to reduce the non-emergency use hours for testing, maintenance and reliability from SO to 37 hours per year.

Contact Information

Name
Cameron Fee
Agency Name
BAAQMD
Job Title
Air Quality Engineer
Contact Types
Responsible Agency

Name
Rebecca Bustos
Agency Name
City of Santa Clara
Job Title
Associate Planner
Contact Types
Lead/Public Agency

Name
Rob Gire
Agency Name
Vantage Data Centers
Job Title
Construction Manager
Contact Types
Project Applicant

Location

Cities
Santa Clara
Counties
Santa Clara
Regions
Countywide
Cross Streets
Lafayette Street

Notice of Determination

Approving Agency
Bay Area Air Quality Management District
Approving Agency Role
Responsible Agency
Approved On
County Clerk
Santa Clara
Final Environmental Document Available at
https://santaclara.legistar.com/LegislationDetail.aspx?ID=6719610&GUID=3C7EA131-557E-43B6-9001-A7708AA5C83C&Options=&Search=

Determinations

(1) The project will have a significant impact on the environment
Yes
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
No
(4) A mitigation reporting or monitoring plan was adopted for this project
No
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
No

Attachments

Disclaimer: The Governor’s Office of Planning and Research (OPR) accepts no responsibility for the content or accessibility of these documents. To obtain an attachment in a different format, please contact the lead agency at the contact information listed above. For more information, please visit OPR’s Accessibility Site.