McLaren Data Center Project

4 Documents in Project

Summary

SCH Number
2018062057
Lead Agency
Energy Commission (California Energy Commission)
Document Title
McLaren Data Center Project
Document Type
NOD - Notice of Determination
Received
Posted
12/14/2018

Document Description
The Bay Air Quality Management District has issued an authority to construct for the McLaren Backup Generating Facility. The MBGF will provide emergency backup power for the McLaren Data Center. When fully built out, the MDC will consist of three four-story, 175,000-180,000 sq. ft. data center buildings and a paved parking lot on a 9-acre site. The MBGF will consist of 15-16 diesel fired backup generators for each data center building to provide emergency backup power for the buildings servers in the event of a power outage. There will also be one additional generator for each building to provide emergency power for fire suppression and other life safety systems. The project also includes switchgear and distribution cabling to connect the 3 generation yards to their respective buildings and 14,250-sq. ft Silicon Valley Power substation along Mathew Street. See: NOD for full description

Contact Information
Ariana Husain
Bay Air Quality Management District
375 Beale St., Suite 600
San Francisco, CA 94105

Phone : (415) 479-8433

Location

Cities
Santa Clara
Counties
Santa Clara
Cross Streets
651, 725, & 825 Matthew Street

Notice of Determination

Approving Agency
Bay Area Quality Management District
Approving Agency Role
Responsible Agency
Approved On
Final Environmental Document Available at
375 Beale St., Suite 600, San Francisco, CA 94105

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
No
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
Yes
Download CSV New Search