Addendum to the Tahoe Cross-County Lodge Replacement and Expansion Project Environmental Impact Report (EIR)

6 Documents in Project

Summary

SCH Number
2018062045
Lead Agency
Tahoe City Public Utility District
Document Title
Addendum to the Tahoe Cross-County Lodge Replacement and Expansion Project Environmental Impact Report (EIR)
Document Type
NOD - Notice of Determination
Received
Posted
9/20/2024
Document Description
In February 2021, the Tahoe City Public Utility District (TCPUD) Board of Directors certified the Environmental Impact Report (EIR) for the Tahoe Cross-Country Lodge Replacement and Expansion Project (approved project) and approved the project. During the final design conducted in support of project permitting, the design team incorporated required mitigation measures identified in the certified EIR and completed additional consultation with utility providers. As the final design elements progressed, it was identified that the primary change to the approved project would require an alternate route for a utility conduit connecting the project site to an existing utility conduit to accommodate operation of the project. The route of this utility corridor was selected because it would avoid the need to make substantial service upgrades in Polaris Road to make the new connection, it would cost less, and based on discussions with Liberty Utilities would be easier to maintain and would involve less disturbance than the original route considered in the certified EIR. This is to advise that TCPUD as the lead agency approved the above-described modifications to the project on September 8, 2024 and have made the following determinations regarding the above-described project: 1. An EIR was not prepared for this project. An addendum to the certified Tahoe Cross-Country Lodge Replacement and Expansion Project EIR was prepared. 2. The project will have a significant effect on the environment. 3. Mitigation measures were made a condition of approval of the project. 4. A mitigation reporting/monitoring plan (MMRP) was not adopted for this project. Applicable, adopted mitigation measures of the Tahoe Cross-Country Lodge Replacement and Expansion Project EIR would be implemented. 5. A Statement of Overriding Consideration was not adopted for this project. 6. Findings were made pursuant to the provisions of CEQA. This is to certify that the Addendum to the Tahoe Cross-Country Lodge Replacement and Expansion Project EIR is available to the General Public and can be viewed online at https://www.tcpud.org/capital-improvement-projects/tahoe-cross-country-lodge-replacement-and-expansion.

Contact Information

Name
Kim Boyd
Agency Name
Tahoe City Public Utility District
Job Title
Director of Strategic Affairs
Contact Types
Lead/Public Agency

Location

Counties
El Dorado, Placer
Regions
Northern California
Zip
96145
Other Location Info
A 5.2-acre site at Polaris Road and Village Road in Tahoe City, Placer County, California

Notice of Determination

Approving Agency
Tahoe City Public Utility District
Approving Agency Role
Lead Agency
Approved On
County Clerks
El Dorado, Placer
Final Environmental Document Available at
https://www.tcpud.org/capital-improvement-projects/tahoe-cross-country-lodge-replacement-and-expansion.

Determinations

(1) The project will have a significant impact on the environment
Yes
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
Yes
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
No
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
Yes (Addendum)
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
No
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
Yes

Attachments

Disclaimer: The Governor’s Office of Planning and Research (OPR) accepts no responsibility for the content or accessibility of these documents. To obtain an attachment in a different format, please contact the lead agency at the contact information listed above. For more information, please visit OPR’s Accessibility Site.

Download CSV New Search Print