Freedom Sewer Rehabilitation Project
4 Documents in Project
Download CSV
New Search
Print
Summary
- SCH Number
- 2018062014
- Lead Agency
- Santa Cruz County
- Document Title
- Freedom Sewer Rehabilitation Project
- Document Type
- NOD - Notice of Determination
- Received
- Posted
- 7/27/2018
- Present Land Use
- single fam res (R-1-6, R-1-8, R-1-10), Multiple family res (RM-2-R), Parks, rec and open space
- Document Description
- The Freedom County Sanitation District is proposing the Freedom Sewer Rehabilitation Project. The project includes the replacement of approx 5 miles of existing wastewater collection lines, located predominately within existing paved roadways in residential neighborhoods. The project area is divided into five improvement locations within the FCSD service area.
- Contact Information
-
Kathleen Molloy
Santa Cruz County
Lead/Public Agency
701 Ocena St., 4th Floor
Santa Cruz, CA 95060
Phone : (831) 454-2123
Location
- Coordinates
- 36°57'2.50"N °45'53.2"W
- Cities
- Watsonville
- Counties
- Santa Cruz
- Cross Streets
- Green Valley Rd and Buena Vista Rd
- Zip
- 95076
- Total Acres
- 27,440 lf
- State Highways
- 1
- Airports
- Watsonville Municipal Airport
- Schools
- Calabasas & Amesti ES
- Waterways
- Pinto Lake, Corralitos Creek, College Lake
- Township
- 20
- Range
- variab
- Section
- 11S
Notice of Determination
- Approving Agency
- County of Santa Cruz
- Approving Agency Role
- Lead Agency
- Approved On
- Final Environmental Document Available at
- 701 Ocean St., 4th floor, Santa Cruz, CA 95060
Determinations
- (1) The project will have a significant impact on the environment
- No
- (2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
- No
- (2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
- Yes
- (2c) An other document type was prepared for this project pursuant to the provisions of CEQA
- No
- (3) Mitigated measures were made a condition of the approval of the project
- Yes
- (4) A mitigation reporting or monitoring plan was adopted for this project
- N/A
- (5) A Statement of Overriding Considerations was adopted for this project
- No
- (6) Findings were made pursuant to the provisions of CEQA
- Yes
Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613.