Hillsdale Middle School Field Lighting Project

2 Documents in Project

Summary

SCH Number
2018061059
Lead Agency
Cajon Valley Union School District (CVUSD)
Document Title
Hillsdale Middle School Field Lighting Project
Document Type
NOD - Notice of Determination
Received
Posted
8/23/2018
Present Land Use
PLU: Athletic fields; Z: Res - variable; GPD: Public/semi public facilities
Document Description
The district intends to install field lighting at its athletic fields at Hillsdale MS. No field lighting is currently installed. Lighting would be installed at the existing football/soccer field and at the three existing baseball/softball fields. The baseball/softball fields are located to the west of the football/soccer field and near the intersection of Brabham St and Fury Lane. Up to 32 light emitting diode fixtures would be installed atop 4 new steel poles (60-80 ft high) erected near the football field. Lighting for the baseball/softball fields would include up to 60 total LED fixtures installed atop 10 new galvanized steel poles. New steel poles would be erected around the perimeter of the baseball/softball field area.

Contact Information

Name
Sharon Dobbins
Agency Name
Cajon Valley Union School District
Contact Types
Lead/Public Agency

Location

Cities
El Cajon
Counties
San Diego
Cross Streets
1301 Brabham St
Zip
92019
Total Acres
9.9
Parcel #
504-040-22, -023
State Highways
SR 67, SR 54
Schools
Hillsdale MS, Cuyamaca College, Rancho SD ES, Valhalla HS, Fuert
Waterways
Sweetwater River
Township
16S
Range
1W
Section
25
Other Information
Vista Grande ES

Notice of Determination

Approving Agency
Cajon Valley Union School District
Approving Agency Role
Lead Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
No

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613.

Download CSV New Search Print