San Luis Rey Habitat Management Area Restoration Project

2 Documents in Project

Summary

SCH Number
2018061020
Lead Agency
San Diego County Water Authority
Document Title
San Luis Rey Habitat Management Area Restoration Project
Document Type
NOD - Notice of Determination
Received
Posted
8/29/2018
Present Land Use
PLU: Ag; Z: Holding area (S90); GPD: Rural lands
Document Description
The project entails establishment and restoration of wetland and upland habitat within a property owned by the Water Authority adjacent to the San Luis Rey River that currently supports row-crop production. The project would require excavating soil from a portion of the site to expand the area suitable for wetland and riparian habitats and the site's active floodplain father north. The property is identified in the Water Authority's Subregional Natural Community Conservation Plan/Habitat Conservation Plan and Programmatic Master Plan Permit as a wetland establishment project to serve as habitat-based mitigation credits that are needed for future Water Authority projects and activities that have an impact on native habitat and associated covered species.

Contact Information

Name
Don Chadwick
Agency Name
San Diego County Water Authority
Contact Types
Lead/Public Agency

Location

Cities
Fallbrook
Counties
San Diego
Cross Streets
SR 76 and Old Hwy 395
Zip
92028
Total Acres
47.64
Parcel #
1250801900, 1250903600
State Highways
SR 76; I-15
Schools
Sullivan MS; Bonsall HS
Waterways
San Luis Rey River

Notice of Determination

Approving Agency
San Diego County Water Authority
Approving Agency Role
Lead Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
No

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above.

Download CSV New Search Print