South Apple Valley Interceptor Project
2 Documents in Project
Download CSV
New Search
Print
Summary
- SCH Number
- 2018061010
- Lead Agency
- Victor Valley Wastewater Reclamation Authority
- Document Title
- South Apple Valley Interceptor Project
- Document Type
- NOD - Notice of Determination
- Received
- Posted
- 7/19/2018
- Present Land Use
- Specific Plan
- Document Description
- The Victor Valley Wastewater Reclamation Authority is proposing to relocate approximately 2,600 lineal feet of a wastewater transmission line to an upland area adjacent to and outside of the flow path of Deser Knolls Wash in Apple Valley. The South Apple Valley INterceptor (project) will consist of construction of new pipeline and related infrastructure in the upland area outside and adjacent to the wash and abandoning in place the old interceptor piepline. The purpose of the project is to reduce the interceptor pipelline. The prupose of the project is to reduce the interceptor pipeline's exposure to damage during major storm events. The new alignment would be entirely outside of the jurisdictional boundaries of Desert Knolls Wash.
- Contact Information
-
Logan Olds
Victor Valley Wastewater Reclamation Authority
20111 Shay Road
Victorville, CA 92394
Phone : (760) 508-7819
Location
- Coordinates
- 34°32'3.41"N 117°16'33"W
- Cities
- Apple Valley
- Counties
- San Bernardino
- Cross Streets
- Potomac Rd
- Total Acres
- 14
- State Highways
- 18
- Schools
- Lewis Center
- Waterways
- Desert Knolls Wash
- Township
- 5N
- Range
- 4W
- Section
- 10
- Base
- SBBM
Notice of Determination
- Approving Agency
- Victor Valley Wastewater Reclamation Authority
- Approving Agency Role
- Lead Agency
- Approved On
- Final Environmental Document Available at
- 20111 Shay Road, Victorville, CA 92394
Determinations
- (1) The project will have a significant impact on the environment
- No
- (2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
- No
- (2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
- Yes
- (2c) An other document type was prepared for this project pursuant to the provisions of CEQA
- No
- (3) Mitigated measures were made a condition of the approval of the project
- Yes
- (4) A mitigation reporting or monitoring plan was adopted for this project
- N/A
- (5) A Statement of Overriding Considerations was adopted for this project
- No
- (6) Findings were made pursuant to the provisions of CEQA
- Yes
Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613.