South Apple Valley Interceptor Project

2 Documents in Project

Summary

SCH Number
2018061010
Lead Agency
Victor Valley Wastewater Reclamation Authority
Document Title
South Apple Valley Interceptor Project
Document Type
NOD - Notice of Determination
Received
Posted
7/19/2018
Present Land Use
Specific Plan
Document Description
The Victor Valley Wastewater Reclamation Authority is proposing to relocate approximately 2,600 lineal feet of a wastewater transmission line to an upland area adjacent to and outside of the flow path of Deser Knolls Wash in Apple Valley. The South Apple Valley INterceptor (project) will consist of construction of new pipeline and related infrastructure in the upland area outside and adjacent to the wash and abandoning in place the old interceptor piepline. The purpose of the project is to reduce the interceptor pipelline. The prupose of the project is to reduce the interceptor pipeline's exposure to damage during major storm events. The new alignment would be entirely outside of the jurisdictional boundaries of Desert Knolls Wash.

Contact Information

Name
Logan Olds
Agency Name
Victor Valley Wastewater Reclamation Authority
Contact Types
Lead/Public Agency

Location

Cities
Apple Valley
Counties
San Bernardino
Cross Streets
Potomac Rd
Total Acres
14
State Highways
18
Schools
Lewis Center
Waterways
Desert Knolls Wash
Township
5N
Range
4W
Section
10
Base
SBBM

Notice of Determination

Approving Agency
Victor Valley Wastewater Reclamation Authority
Approving Agency Role
Lead Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
Yes

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613.