Walnut Grove Pump Station Abandonment Project (Streambed Alteration Agreement No. 1600-2018-0242-R3)
4 Documents in Project
Summary
SCH Number
2018052078
Lead Agency
Sacramento Area Sewer District
(SASD)
Document Title
Walnut Grove Pump Station Abandonment Project (Streambed Alteration Agreement No. 1600-2018-0242-R3)
Document Type
NOD - Notice of Determination
Received
Posted
1/31/2019
Present Land Use
Agriculure-20 and Special Planning Area/Agricultural cropland and low density residential
Document Description
The Central Valley Regional Water Board is issuing a 401 Water Quality Certification for the subject project. The project entails placing a 16-inch diameter gravity pipeline following the route of an existing 8-inch diameter forced main sewer line. The new pipeline will begin at Pump Station S064 and continue southeast parallel to ditch AGD1 for approximately 1,270 feet and cross a lateral agricultural ditch. The pipeline will then turn to the northeast for approximately 190 feet and cross a second lateral ditch, turn to the southeast again and travel approximately 500 feet along the adjacent agricultural land until reaching Pump Station S146. The gravity pipeline will outfall into the influent manhole at Pump Station S146. The total length of the new pipeline will be approximately 2,000 feet, with manholes place no more than 500 feet apart. The existing 8-inch force main will be abandoned in place.
Contact Information
Name
Peter Minkel
Agency Name
Central Valley Regional Water Board
Contact Types
Lead/Public Agency
Phone
Location
Coordinates
Counties
Sacramento
Zip
95690
Total Acres
2.63
State Highways
SR 160
Schools
Walnut Grove Elementary
Waterways
Snodgrass Slough and Mokelumne River
Township
5N
Range
4E
Section
35
Other Location Info
Walnut Grove
Other Information
Walnut Grove
Notice of Determination
Approving Agency
Central Valley Regional Water Board
Approving Agency Role
Responsible Agency
Approved On
Determinations
(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
Yes
Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above.