Butano Creek Channel Reconnection and Resilience Project

3 Documents in Project

Summary

SCH Number
2018052007
Lead Agency
San Mateo County Resource Conservation District
Document Title
Butano Creek Channel Reconnection and Resilience Project
Document Type
NOD - Notice of Determination
Received

Document Description
The California Department of Fish and Wildlife has executed Lake and Streambed Alteration Agreement number 1600-2018-0137-R3, pursuant to section 1602 of the Fish and Game Code to the project applicant, the San Mateo Resource Conservation District. The project includes following activities: Channel excavation to increase conveyance of flood flows and sediment downstrea. The project will increase the conveyance capacity of Butano Creek by increasing the cross-sectional area of the channel and creating a uniform slope of 0.04 percent or roughly a 2.7 foot change in elevation over 7,400 linear feet. Augmentation of an existing, upper floodplain berm, located upstream of Pescadero Creek Rd. Improvements to an existing berm at two locations in Butano Marsh along the reconnected Butano Creek to help maintain the excavated channel. Upgrade an existing marsh control structure. Beneficially reusing sediment removed from Butano Creek to improve water quality and reduce fish kills.

Contact Information
Randi Adair
CDFW, Bay Delta Region
2825 Cordelia Rd, Suite 100
Fairfield, CA 95434

707-576-2786

Location

Coordinates
37.253000°'"N 122.400000°'"W
Counties
San Mateo
Cross Streets
Pescadero Creek Rd, hwy 1
Zip
94060
Total Acres
44
Parcel #
multiple
State Highways
1
Schools
mult
Township
8S
Range
5W
Section
4,5,8,
Base
Diablo
Other Location Info
Pescadero

Notice of Determination

Approving Agency
CDFW
Approving Agency Role
Responsible Agency
Approved On
Final EIR Available Location
N/A

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A Statement of Overriding Considerations was adopted for this project
No
(5) Findings were made pursuant to the provisions of CEQA
No