Horsethief Canyon Water Reclamation Facility Upgrades and Expansion Project

3 Documents in Project

Summary

SCH Number
2018051070
Lead Agency
Elsinore Valley Municipal Water District
Document Title
Horsethief Canyon Water Reclamation Facility Upgrades and Expansion Project
Document Type
NOD - Notice of Determination
Received
Posted
8/28/2018
Present Land Use
The propose dproject would be located on the existing HTCWRF site, which is designated MDR in the 2017 Elsinore Area Plan.
Document Description
The HTCWRF upgrades and expansion involve construction of an additional waste water treatment process train for secondary treatment using conventional activated sludge with an anoxic zone for nitrification/denitrification and a secondary clarifier, filtration and chlorine disinfection. The proposed project includes modifications to the existing headworks, a new raw sewage diversion box, a new dewatering system, a new truck loading facility, two new pond pump stations, and additional modifications to existing facilities. The Proposed project would provide an additional 0.3 million gallons per day (mgd) of treatment capacity, expanding the total treatment capacity of HTCWRF from 0.5 to 0.8 mgd annual average flow.

Contact Information

Name
Parag Kalaria
Agency Name
Elsinore Valley Municipal Water District
Contact Types
Lead/Public Agency

Location

Cities
Corona
Counties
Riverside
Cross Streets
Horsethief Canyon/Shotgun Trail
Zip
92883
Total Acres
9.03
Parcel #
393180002
State Highways
I-15
Schools
Luiseno Elementary School
Township
5S
Range
5W
Section
17
Base
SB

Notice of Determination

Approving Agency
Elisnore Valley Municipal Water District
Approving Agency Role
Lead Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
Yes

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613.

Download CSV New Search Print