Regional Water Reclamation Facility Upgrade and Expansion
4 Documents in Project
Download CSV
New Search
Print
Summary
- SCH Number
- 2018051053
- Lead Agency
- Elsinore Valley Municipal Water District
- Document Title
- Regional Water Reclamation Facility Upgrade and Expansion
- Document Type
- NOD - Notice of Determination
- Received
- Posted
- 7/31/2018
- Present Land Use
- Public Institutionl/PI (Public Institutional)
- Document Description
- EVMWD proposes to expand its Regional Water Reclamation Facility from an existing capacity of 8 million gallons per day (MGD) to 12 MGD. The project would include a 4-MGD capacity expansion using membrane bioreactor (MBR) and ultraviolet treatment processes. The proposed expansion would add a new train with MBR and UV treatment processes. Train C would offer two biological nutrient removal trails with a new MBR.
- Contact Information
-
Parag Kalaria
Elsinore Valley Municipal Water District
31315 Chaney Street
Lake Elsinore, CA 92530
Phone : (951) 674-3146
Location
- Coordinates
- 33°40'52.99"N 117°20'41.99"W
- Cities
- Lake Elsinore
- Counties
- Riverside
- Cross Streets
- Treleven Ave, Strickland Ave
- Zip
- 92530
- Total Acres
- 55
- Parcel #
- 377120020, 377130021, 377130032, 377140009, 377140012, 377140015
- State Highways
- SR-74, I-15
- Schools
- Various
- Waterways
- Temescal Creek, Lake Elsinore, Gunnerson Pond
- Township
- 5S
- Range
- 4W
- Section
- 31
- Base
- MDB&M
Notice of Determination
- Approving Agency
- Elsinore Valley Municipal Water District
- Approving Agency Role
- Lead Agency
- Approved On
- Final Environmental Document Available at
- 31315 Chaney Street, Lake Elsinore, CA 92530
Determinations
- (1) The project will have a significant impact on the environment
- No
- (2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
- No
- (2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
- Yes
- (2c) An other document type was prepared for this project pursuant to the provisions of CEQA
- No
- (3) Mitigated measures were made a condition of the approval of the project
- Yes
- (4) A mitigation reporting or monitoring plan was adopted for this project
- N/A
- (5) A Statement of Overriding Considerations was adopted for this project
- No
- (6) Findings were made pursuant to the provisions of CEQA
- No
Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613.