City of Paso Robles Recycled Water Distribution System Project

2 Documents in Project

Summary

SCH Number
2018051033
Lead Agency
Paso Robles, City of (City of Paso Robles)
Document Title
City of Paso Robles Recycled Water Distribution System Project
Document Type
NOD - Notice of Determination
Received
Posted
8/30/2018
Present Land Use
PF, Parks/OS, AG, Busines park, residential single fam, and commercial service

Document Description
The city proposes to construct a recycled water distribution system that would divert disinfected tertiary municipal wastewater from the city's existing wastewater treatment facility to various non-potable uses within the city and surrounding areas. The proposed project consists of an initial phase of construction and delivery of recycled water to identified potential near-term users, and a possible future extension of the distribution system to serve additional areas of Paso Robles and surrounding unincorporated areas in the future. The system would generally consist of recycled water pipelines (6-24 in diameter), a recycled water pump station, storage tank, and discharge of surplus recycled water to the Salinas River and Huer Huero Creek.

Contact Information
Susan DeCarli
City of Paso Robles
1000 Spring Street
Paso Robles, CA 93446

Phone : (805) 237-3970

Location

Coordinates
35°38'17"N 120°41'15"W
Cities
Paso Robles
Counties
San Luis Obispo
Cross Streets
mult
Zip
93446
Total Acres
22
Parcel #
008-51-002, 020-211-015
State Highways
US 101, SR 46
Railways
UPRR
Airports
Paso Robles Municipal Airport
Schools
mult
Waterways
Huer Huero Creek, Salinas River
Township
26S
Range
12E
Section
21
Base
MDBM

Notice of Determination

Approving Agency
City of Paso Robles
Approving Agency Role
Lead Agency
Approved On
Final EIR Available Location
1000 Spring Street, Paso Robles, CA 93446

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A Statement of Overriding Considerations was adopted for this project
No
(5) Findings were made pursuant to the provisions of CEQA
Yes