Minor Discretionary Permit 2017-20 (Sodequist Warehouse Expansion)
3 Documents in Project
Summary
SCH Number
2018042073
Lead Agency
City of Turlock
Document Title
Minor Discretionary Permit 2017-20 (Sodequist Warehouse Expansion)
Document Type
NOD - Notice of Determination
Received
Posted
7/10/2018
Present Land Use
Industrial
Document Description
The applicant is requesting approval to construct a new 23,200 sq. ft. warehouse building on the remaining undeveloped portion of land located at 303 & 305 South Soderquist Road (Stanislaus County APN 050-001-024). The site is currently developed with two existing warehouse buildings totaling approx. 71,190 sq. ft. The expansion will include nine additional truck docks and five new parking spaces for a total of 95 on-site parking spaces for guest and employees. A 10 foot tall sound wall will be constructed along the southeast corner of the proposed warehouse along South Soderquist Road. The sound wall will be constructed with perforated metal and contain facade elements and colors similar to the main structure. On-site improvements will include the installation of additional parking, paving, landscaping, and street trees.
Contact Information
Name
Don Phillips
Agency Name
City of Turlock
Contact Types
Lead/Public Agency
Phone
Location
Cities
Turlock
Counties
Stanislaus
Cross Streets
South Sodequist and West Main St.
Zip
95380
Total Acres
4.866
Parcel #
050-001-024
State Highways
99
Railways
UPRR
Schools
4
Township
5S
Range
10E
Section
22
Base
MDBM
Other Location Info
Keyes, Denair
Notice of Determination
Approving Agency
City of Turlock
Approving Agency Role
Lead Agency
Approved On
Determinations
(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
Yes
Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above.