Hill 9 & 10 and Branding Consolidation Phase 1 (Streambed Alteration Agreement No. 1600-2018-0196-R2)

3 Documents in Project

Summary

SCH Number
2018042066
Lead Agency
Cobb Area County Water District
Document Title
Hill 9 & 10 and Branding Consolidation Phase 1 (Streambed Alteration Agreement No. 1600-2018-0196-R2)
Document Type
NOD - Notice of Determination
Received
Posted
8/27/2018
Present Land Use
varies, primarily in existing roadways

Document Description
CDFW has executed Streambed Alteration Agreement Number 1600-2018-0196 -R2, pursuant to section 1602 of the Fish and Game Code to the project applicant, Cobb Area County Water District. The project is limited to the installation of a 20 foot by 10.5 clear-span vehicle bridge across Cole Creek to facilitate access to a new water treatment building. The bridge will be a metal deck bridge with reinforced concrete bridge abutments. The existing 18 foot by 3.5 foot wooden bridge will be removed. The project also includes removal of Himalayan blackberry and one 20-inch black oak trees.

Contact Information
Kelsey Vella
CDFW
1701 Nimbus Rd, Suite A
Rancho Cordova, CA 95670

Phone : (916) 358-4315

Location

Coordinates
38.901845°'"N 122.752024°'"W
Counties
Lake
Cross Streets
9105 State Route 175
Zip
95426
Total Acres
.08
Parcel #
varies
State Highways
175
Waterways
Cole Creek
Township
12N
Range
8W
Section
9
Base
MDB
Other Location Info
Cobb
Other Information
Kelseyville, CA

Notice of Determination

Approving Agency
CDFW
Approving Agency Role
Responsible Agency
Approved On
Final Environmental Document Available at
N/A

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
No

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613.