Dogtown Road over Indian Creek Bridge Replacement Project Initial Study/MND

2 Documents in Project

Summary

SCH Number
2018042055
Lead Agency
Calaveras County
Document Title
Dogtown Road over Indian Creek Bridge Replacement Project Initial Study/MND
Document Type
NOD - Notice of Determination
Received
Posted
8/20/2018
Present Land Use
county roadway ROW - surrounding land uses: resource production. Z: Unclassified
Document Description
The county proposes to replace the existing bridge with a single span, precast, pre-stressed concrete, voided slab bridge. The corresponding roadway improvements will consist of a paved roadway width of 24 ft at the bridge. To transition from the bridge to the existing roadway width, the county will reconstruct approx 275 ft of Dogtown Rd on both sides of the bridge. Demolition of the old bridge and construction of the new bridge and approach road would take approx six months. Overall, project construction activities would occur during the summer/early fall months when water levels are at their lowest.

Contact Information

Name
Evan Weston
Agency Name
Calaveras County
Contact Types
Lead/Public Agency

Location

Cities
Angels Camp
Counties
Calaveras
Cross Streets
Dogtown Rd
Total Acres
<1
Parcel #
county ROW
State Highways
49
Waterways
Indian Creek
Township
13N
Range
13E
Section
5

Notice of Determination

Approving Agency
Board of Supervisors of Calaveras County
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
Yes

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613.

Download CSV New Search Print