John Adams Middle School Auditorium Replacement Project

2 Documents in Project

Summary

SCH Number
2018031064
Lead Agency
Santa Monica-Malibu Unified School District
Document Title
John Adams Middle School Auditorium Replacement Project
Document Type
NOD - Notice of Determination
Received

Document Description
The proposed project would involve construction of a new performing arts center at the site of the existing auditorium and music building at the John Adams MS Campus. The proposed project would address the existing structural safety concerns at the auditorium and would also expand the performing arts space available on the site to meet existing school needs. The proposed performing arts center would be developed over the course of several phases, the first of which would involve renovating the existing music building, removing the existing auditorium, and reconstructing a new auditorium. The second phase would involve constructing a rehearsal building, and the third phase would involve replacing the music building.

Contact Information
Carey Upton
Santa Monica-Malibu Unified School District
1651 16th St
Santa Monica, CA 90404

310-399-5865 x 79383

Location

Coordinates
34°00'52"N 118°28'13"W
Cities
Santa Monica
Counties
Los Angeles
Cross Streets
Pearl St, 16th St and 17th St
Zip
90405
Total Acres
1.07
Parcel #
SR 1
State Highways
SR 1
Railways
Metro
Airports
Santa Monica Airport
Schools
numerous
Township
2S
Range
15W
Section
08

Notice of Determination

Approving Agency
Santa Monica-Malibu Unified School District
Approving Agency Role
Lead Agency
Approved On
Final EIR Available Location
1651 16th St., Santa Monica, CA 90404

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A Statement of Overriding Considerations was adopted for this project
No
(5) Findings were made pursuant to the provisions of CEQA
Yes