State Route 74 Safety Improvement Project

4 Documents in Project

Summary

SCH Number
2018031005
Lead Agency
California Department of Transportation, District 12
Document Title
State Route 74 Safety Improvement Project
Document Type
NOD - Notice of Determination
Received
Posted
1/4/2019
Present Land Use
highway/transportation
Document Description
The project proposes to improve the segment of SR-74 from 0.8 mile west of the San Juan Hot Springs Canyon to the Orange/Riverside County line, excluding the San Juan Canyon Bridge IPM 13.28-13.33). The purpose of this project is to reduce the number and severity of collisions by applying High Friction Surface Treatment to the existing asphalt concrete roadway surface to address wet pavement-related collisions; constructing a continuous 4-ft shoulder in both directions and bringing existing non-standard lanes to standard 12 ft lanes from PM 11.50 to PM 13.28; providing superelevation improvements and constructing 10 ft shoulders at the San Juan Fire Station; and will add safety lighting at the San Juan Fire Station (PM 12.302-12.50) and drainage improvements to divert sheet flow.

Contact Information

Name
Carmen Lo
Agency Name
California Department of Transportation, District 12
Contact Types
Lead/Public Agency

Location

Cities
San Juan Capistrano
Counties
Orange
Cross Streets
Caspers Park Rd to the south; Vista Rd to the north
Total Acres
36.81
Airports
McConville Airstrip
Waterways
San Juan Creek
Township
6S7S
Range
6W
Section
35/3

Notice of Determination

Approving Agency
Caltrans
Approving Agency Role
Lead Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
Yes

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above.