The project will replace an existing portion of Kammerer Road with a four-lane thoroughfare, construct a new four-lane expressway section to Interstate 5, and implement railroad grade separation and interchange improvements. The total length of the Project is approximately 5.75 miles, and, dependent upon funding, initial construction may consist of a two-lane facility. As funding and traffic conditions warrant, the four-lane facility will be constructed. The purpose of the project is to improve regional traffic operations, reduce existing and projected congestion, and provide a vital component of the east-west gap closure.
Contact Information
Name
Brigitte Driller
Agency Name
California Transportation Commission
Job Title
Associate Deputy Director
Contact Types
Responsible Agency
Address
Phone
Location
Regions
Northern California
Other Location Info
The project is located on Kammerer Road from Interstate 5 to State Route 99 within Sacramento County and the City of Elk Grove.
Notice of Determination
Approving Agency
California Transportation Commission
Approving Agency Role
Responsible Agency
Approved On
County Clerk
Sacramento
Final Environmental Document Available at
City of Elk Grove, 1st Floor at the Development Services Counter, 8401 Laguna
Palms Way, Elk Grove, CA 95758
Determinations
(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
Yes
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
No
Attachments
Notice of Determination
Disclaimer: The Governor’s Office of Planning and Research (OPR) accepts no responsibility for the content or accessibility of these documents. To obtain an attachment in a different format, please contact the lead agency at the contact information listed above. For more information, please visit OPR’s Accessibility Site.