Whittier Boulevard/Colima Road Intersection Improvement Project

3 Documents in Project

Summary

SCH Number
2018021058
Lead Agency
Whittier, City of (City of Whittier)
Document Title
Whittier Boulevard/Colima Road Intersection Improvement Project
Document Type
NOD - Notice of Determination
Received
Posted
5/23/2018

Document Description
The proposed project would provide intersection improvements consisting of an additional northbound left-turn lane along Colma Rd; increase the southbound left- and right-turn storage along Colima Rd; construct new curb and gutter and sidewalks on the northbound side of Colima Rd in the southeast quadrant of the intersection; increase the westbound left-turn storage along the Whittier Blvd; provide a westbound right turn pocket along Whittier Blvd; and construct a new retaining wall, new curb and gutter, and sidewalks on the westbound side of Whittier Blvd in the northeast quadrant of the intersection. Additionally, an option is proposed that would include improvements to Colima Rd only.

Contact Information
Carl Hassel
City of Whittier
13230 Penn Street
Whittier, CA 90602

Phone : (562) 567-9505

Location

Coordinates
33°56'55.7"N 118°00'23.5"W
Cities
Whittier
Counties
Los Angeles
Cross Streets
Whittier Blvd /Colima Rd
Zip
90602
Total Acres
4.5
Parcel #
numerous
State Highways
72
Railways
SPRR
Schools
Numerous
Township
2S
Range
11W
Section
35
Base
SBM

Notice of Determination

Approving Agency
City of Whittier
Approving Agency Role
Lead Agency
Approved On
Final Environmental Document Available at
13230 Penn St., Whittier, CA 90602

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
No

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613.