Inglewood Basketball and Entertainment Center (IBEC) Project

5 Documents in Project

Summary

SCH Number
2018021056
Lead Agency
City of Inglewood
Document Title
Inglewood Basketball and Entertainment Center (IBEC) Project
Document Type
NOD - Notice of Determination
Received
Posted
7/22/2020
Present Land Use
General Plan designations: Industrial and Commercial. Zoning: C-2A Airport Commercial, M-1L Limited Manufacturing, P-1 Parking, R-2 Residential Limited Multifamily, R-3 Residential Multiple Family. Portions of the project site are vacant.
Document Description
The Project consists of an approximately 915,000-square foot (sf) Arena intended to promote the enjoyment and recreation of the public, and designed to host the LA Clippers basketball team with up to 18,000 fixed seats for National Basketball Association (NBA) games, and with up to 500 additional temporary seats for other events such as family shows, concerts, corporate and community events, and other sporting events; an up to 85,000-square foot team practice and athletic training facility; up to 71,000-square feet of LA Clippers office space; an approximately 25,000 square foot sports medicine clinic; up to 63,000 square feet of ancillary and related arena uses including retail and dining; an outdoor plaza adjacent to the arena; parking facilities; relocation of a City of Inglewood groundwater well; and various circulation, infrastructure, and other ancillary uses (the Project). The Project will also include a limited service hotel. Annually, it is expected that the LA Clippers will host up to five preseason games in October; 41 regular season games from October to mid-April; and an average of three playoff games from April to June based on NBA team averages. Other events such as concerts, family shows, conventions and corporate or civic events, and non-LA Clippers sporting events will take place in the Arena throughout the year, with attendance ranging from small events up to 2,000 attendees (average of 300 attendees) to full Arena capacity. A six-story parking structure containing approximately 3,110 parking spaces will be located within the West Parking Garage Site. A 17-foot-high pedestrian bridge will span South Prairie Avenue, connecting the West Parking Garage to the Arena Site to provide pedestrian access between the second floor of the parking garage to the second floor of the westernmost building in the plaza. The East Transportation and Hotel Site will include a parking garage (approximately 365 spaces) and transportation hub to accommodate private vehicle parking, private or charter bus staging, and Transportation Network Company staging, pick-up and drop-off. The Project will also include a limited-service hotel use with up to 150 rooms on an approximately 1.3-acre portion of the East Transportation and Hotel Site. The hotel could include amenities such as a lobby, business center, a fitness room, a guest laundry facility, a market pantry, and/or an outdoor gathering area. The hotel will be approximately six stories, with a maximum height of approximately 100 feet. Circulation improvements including driveways, signals, a crosswalk, bicycle parking, relocation of two bus stops, improved sidewalks, and a 17-foot tall pedestrian bridge crossing South Prairie Avenue will be included as part of the Project. A portion of West 102nd Street between South Prairie Avenue and South Doty Avenue will be vacated and included within the Arena Site. Approximately 350 linear feet of West 101st Street will be vacated and developed as part of the West Parking Garage Site. The primary vehicular access to the Project Site will be provided along the major corridors of South Prairie Avenue and West Century Boulevard. Before, during, and after LA Clippers basketball games and other large events, the Project will provide shuttle service that will connect the Project Site to the Metro Green Line's Hawthorne/Lennox Station and the Metro Crenshaw/LAX Line's La Brea/Florence Station. The shuttle service will drop off and pick up attendees at the shuttle pick-up and drop-off location on the west side of the Arena Site along South Prairie Avenue. The Project will also include identification and advertising signage, graphic display panels or systems, potential illuminated rooftop signage, and wayfinding signage. City approvals in furtherance of the Project include: A. the following actions , each of which received final approval by the City Council of the City of Inglewood on July 21, 2020: approval of General Plan Amendment No. 2020-003 to the Land Use, Circulation, and Safety Elements; approval of Specific Plan Amendment No. 2020-001 to the Inglewood International Business Park Specific Plan; and, approval of Sports and Entertainment Complex Design Guidelines; and B. the following actions for which ordinances were introduced and approved for first reading by the City Council of the City of Inglewood on July 21, 2020: adoption of Zone Change No. 2020-001; adoption of Zone Code Amendment No. 2020-002; adoption of Amendments to Inglewood Municipal Code Chapters 2, 3, 5, 10, and 11; and, approval of a Development Agreement between Murphy’s Bowl, LLC and the City of Inglewood.

Contact Information

Name
Mindy Wilcox, AICP
Agency Name
City of Inglewood
Contact Types
Lead/Public Agency

Name
Agency Name
Murphy's Bowl, LLC
Contact Types
Project Applicant

Location

Cities
Inglewood
Counties
Los Angeles
Regions
Citywide
Cross Streets
West Century Blvd and South Prairie Ave
Zip
90303
Total Acres
approx. 28
Jobs
1476
Parcel #
several (see graphic in NOD)
State Highways
I-405, I-105
Airports
Los Angeles International, Hawth
Schools
several
Other Location Info
The Project Site is located in the southwestern portion of the City of Inglewood within Los Angeles County, approximately 10 miles south/southwest of downtown Los Angeles. The Project Site is approximately 28 acres, divided into four sites. The main portion of the Project Site (the Arena Site) is approximately 17 acres and is bounded by West Century Boulevard on the north, South Prairie Avenue on the west, South Doty Avenue on the east, and an imaginary straight line extending east from West 103rd Street to South Doty Avenue to the south. The Project Site includes three additional areas: the West Parking Garage Site on an approximately 5-acre site bounded by West Century Boulevard to the north, hotel and residential uses to the west, South Prairie Avenue to the east, and West 102nd Street to the south; the East Transportation and Hotel Site on an approximately 5-acre site bounded by West Century Boulevard to the north, industrial and commercial uses to the east and west, and West 102nd Street to the south; and the Well Relocation Site on an approximately 0.2-acre parcel located at 3812 West 102nd Street, surrounded by vacant land to the west and south and bounded by residential uses to the east. The Project Site is located immediately to the south of the Hollywood Park Specific Plan (HPSP) area.

Notice of Determination

Approving Agency
City of Inglewood
Approving Agency Role
Lead Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
Yes
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
Yes
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
No
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
Yes
(5) A Statement of Overriding Considerations was adopted for this project
Yes
(6) Findings were made pursuant to the provisions of CEQA
Yes

Attachments

Notice of Determination

Disclaimer: The Governor’s Office of Planning and Research (OPR) accepts no responsibility for the content or accessibility of these documents. To obtain an attachment in a different format, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613. For more information, please visit OPR’s Accessibility Site.

Download CSV New Search Print