Envision: Solar Powered Electric Vehicle Charing Station
Summary
SCH Number
2018018156
Public Agency
San Diego Unified Port District
Document Title
Envision: Solar Powered Electric Vehicle Charing Station
Document Type
NOE - Notice of Exemption
Received
Posted
1/16/2018
Document Description
Project involves the placement of one demonstrative solar powered electric vehicle (EV) charging station from Dec. 4, 2017 to Dec. 8, 2017 at the northern end of the San Diego Unified Port District Administration Building's public parking lot, located at 3165 Pacific Highway in the city of San Diego. The EV charging station would be provided to the District by Envision, the solar developer, at no cost. Upon completion of the demonstration period, it is anticipated the District would purchase an EV charging station in Dec. 2017, and deploy the District owned EV charging station at the Administrative Building's public parking lot in Jan. 2018.
The EV charging station would be approx. 14.5 feet tall and would be placed within a 135 sq. ft. standard vehicle parking space to provide charging capabilities to the space where the station is located and therefore would result in no net loss of parking. The EV charging station would require approx. one truck trip per day for the delivery of the charging station, and would take approx. one day to assemble. Additionally, the EV charging station, and would take approx. one day to assemble. Additionally, the EV charging station is completely solar operated, and would not require electrical hookups or trenching. The EV charging station is also portable and may be relocated to other District facilities throughout tidelands.
Contact Information
Name
Maggie Weber
Agency Name
San Diego Unified Port District
Contact Types
Lead/Public Agency
Phone
Location
Counties
San Diego
Notice of Exemption
Exempt Status
Categorical Exemption
Type, Section or Code
S:15301,15303,15311 Class 1,3,11
Reasons for Exemption
Existing Facilities.
New Construction or Conversion of Small Structures.
Accessory Structures.