Sacramento River West Bank Seepage Mitigation Project

4 Documents in Project

Summary

SCH Number
2017122058
Lead Agency
Sacramento River West Side Levee District
Document Title
Sacramento River West Bank Seepage Mitigation Project
Document Type
NOD - Notice of Determination
Received
Posted
7/17/2018
Present Land Use
ag intensive

Document Description
The project will allow for the construction of approx. 3.25 miles of permanent drained seepage berm along the landside toe of the Sacramento River west levee to prevent erosion of the landside levee toe and possible levee failure. Drainage seepage berms are landside earthen embankment structures that resist accumulated water pressure and safely release seeping water at the landside toe of the berm through an internal rock drainage layer. The 24.7-acre Project will consist of constructing approx. 3.25 miles of seepage berm along the landside levee toe of the right (west) bank of the Sacramento River.

Contact Information
Nicholas White
Central Valley RWQCB
11020 Sun Center Dr. #200
Rancho Cordova, CA 95670

Phone : (916) 464-4856

Location

Coordinates
38°50'50"N 121°43'48"W
Counties
Yolo
Cross Streets
Road 108 and SR 45
Zip
95776
Total Acres
43
Parcel #
056-030-02
State Highways
SR 45
Waterways
Sacramento River
Township
12N
Range
2E
Section
34
Other Location Info
Knights Landing

Notice of Determination

Approving Agency
Central Valley RWQCB
Approving Agency Role
Responsible Agency
Approved On
Final Environmental Document Available at
975 Wilson Bend Road, Grimes, CA 95950

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
No