Healdsburg High School Track and Field Improvements and Gymnasium Expansion

2 Documents in Project

Summary

SCH Number
2017122021
Lead Agency
Healdsburg Unified School District
Document Title
Healdsburg High School Track and Field Improvements and Gymnasium Expansion
Document Type
NOD - Notice of Determination
Received
Posted
2/27/2018
Present Land Use
GP: Public/quasi public; Z: P-public
Document Description
A new gymnasium and locker room should be attached to the existing gym of Healdsburg High School in an area previously used for portable buildings. Daily and seasonal usage of the gym would be unchanged from existing conditions. The track and field improvements would keep the track in its current location but provide new track surfacing and reorient the finish line from the southeast corner of the track to the northwest corner. Emergency vehicle access would be provided on the west side if the field. The football/soccer field set in the center of the track would be synthetic turf with shock pad, soil isolation fabric, compacted leveling course, a sub drain system..

Contact Information

Name
Glen Schaezlein
Agency Name
Healdsburg Unified School District
Contact Types
Lead/Public Agency

Location

Cities
Healdsburg
Counties
Sonoma
Cross Streets
Prince Ave, University Ave, Monte Vista Ave
Zip
95448
Total Acres
27
Parcel #
002-421-002-000
State Highways
101
Schools
Healdsburg MS, Fitch Mountain ES

Notice of Determination

Approving Agency
Healdsburg Unified School District
Approving Agency Role
Lead Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
Yes
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
Yes
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
No
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
Yes
(6) Findings were made pursuant to the provisions of CEQA
No

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613.