Aliso Creek Trail Slope Repairs Project (Streambed Alteration Agreement No. 1600-2015-0115-R5)

3 Documents in Project

Summary

SCH Number
2017121005
Lead Agency
Orange County
Document Title
Aliso Creek Trail Slope Repairs Project (Streambed Alteration Agreement No. 1600-2015-0115-R5)
Document Type
NOD - Notice of Determination
Received

Document Description
CDFW has executed Lake and Streambed Alteration Agreement Number 1600-2015-0115-R5, pursuant to section 1602 of the Fish and Game code to the project Applicant, Orange County Parks. The Aliso Creek Trail Slope Repairs Project will armor four locations within the stream in the project area. One location will incorporate the removal of two 60-inch corrugated metal culverts. The other three streams armoring areas include the installation of rock rip-rap bank protection at erosion sites and potential erosion sites and potential erosion sites within the stream. The project includes the maintenance of the rock rip-rap structures and culvert crossing structure installed as a part of the project. Temporarily stream impacts of up to 0.41 acres will be restored and replanted after construction. Permanent stream impacts of up to 0.16 acre will be mitigated either through the application of credit(s) purchased from a CDFW- approved mitigation bank, or creation of 0.16 acres of in-kind habitat and the restoration or enhancement of 0.32 acres.

Contact Information
Kevin Hupf
CDFW
3883 Ruffin Road
San Diego, CA 92123

858.636.3160

Location

Coordinates
33.6818°'"N -117.6648°'"W
Cities
Laguna Hills
Counties
Orange
Cross Streets
Paseo de Valencia and I-5
Township
6S
Range
8W
Section
34
Base
SBM

Notice of Determination

Approving Agency
CDFW
Approving Agency Role
Responsible Agency
Approved On
Final EIR Available Location
3883 Ruffin Road, San Diego, CA 92123

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A Statement of Overriding Considerations was adopted for this project
No
(5) Findings were made pursuant to the provisions of CEQA
No