Rancho Seco Solar II (Streambed Alteration Agreement No. 1600-2018-0241-R2)
8 Documents in Project
Download CSV
New Search
Print
Summary
- SCH Number
- 2017092042
- Lead Agency
- Sacramento Municipal Utility District
- Document Title
- Rancho Seco Solar II (Streambed Alteration Agreement No. 1600-2018-0241-R2)
- Document Type
- NOD - Notice of Determination
- Received
- Posted
- 9/23/2020
- Document Description
- The Project includes construction and operation of a new photovoltaic (PV) solar power facility and decommissioning and removal of an existing solar power facility. The Project encompasses approximately 554 acres comprised of the PV solar panels, inverters, a substation, switchyard, battery storage and interconnection to the existing transmission system. The amendment includes four (4) components: updating the contact persons, project description, exhibits, and mitigation plan to incorporate the Project’s 100% design plans.
- Contact Information
-
Dylan Wood
California Department of Fish and Wildlife
Lead/Public Agency
1701 Nimbus Road
Rancho Cordova, CA 95670
Phone : (916) 358-2384
dylan.wood@wildlife.ca.gov -
Juan Suarez, Rancho Seco Solar, LLC
Project Applicant
Location
- Coordinates
- 38°20'42"N 121°7'19"W
- Counties
- Sacramento
- Regions
- Northern California
- Cross Streets
- 4960 Twin Cities Road
- Parcel #
- 140-0050-008, 140-0050-0011, 140-0050-0010 and 140-0050-0013
- Township
- 6N
- Range
- 8E
- Section
- 28,29,
- Other Location Info
- Herald
Notice of Determination
- Approving Agency
- California Department of Fish and Wildlife
- Approving Agency Role
- Responsible Agency
- Approved On
- Final Environmental Document Available at
- at the office location listed above for the Lead Agency. CDFW’s record of project approval as Responsible Agency is available at CDFW’s regional office.
Determinations
- (1) The project will have a significant impact on the environment
- No
- (2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
- Yes
- (2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
- No
- (2c) An other document type was prepared for this project pursuant to the provisions of CEQA
- No
- (3) Mitigated measures were made a condition of the approval of the project
- Yes
- (4) A mitigation reporting or monitoring plan was adopted for this project
- No
- (5) A Statement of Overriding Considerations was adopted for this project
- No
- (6) Findings were made pursuant to the provisions of CEQA
- Yes
Attachments
- Notice of Determination
- 2018-0241_Amend #1 NOD PDF 228 K
Disclaimer: The Governor’s Office of Planning and Research (OPR) accepts no responsibility for the content or accessibility of these documents. To obtain an attachment in a different format, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613. For more information, please visit OPR’s Accessibility Site.