West Stanislaus Irrigation District Fish Screen Intake Project

3 Documents in Project

Summary

SCH Number
2017092008
Lead Agency
West Stanislaus Irrigation District (West Stanislaus Irrigation District)
Document Title
West Stanislaus Irrigation District Fish Screen Intake Project
Document Type
NOD - Notice of Determination
Received
Posted
2/20/2018
Present Land Use
extensive ag 40/ag

Document Description
The proposed project would include installation and operation of a new 347 cubic feet per second capacity screened intake with a low-lift pump station located on the bank of the San Joaquin River adjacent to the mouth of the WSID intake canal. The proposed project would also include approx.. 2,100 feet of underground pipeline from the proposed pump station to the intake canal; sediment removal and management along the length of the existing intake canal; upgrading existing roads along the intake canal; two wildlife crossings on the intake canal; and associated facilities.

Contact Information
Bobby Pierce
West Stanislaus Irrigation District
116 E St P.O. Box 37
Westley, CA 95387

Phone : (209) 894-3091

Location

Coordinates
37°36'16.45"N 121°10'40.8"W
Counties
Stanislaus
Cross Streets
E. West Stanislaus Rd, S. River Rd
Zip
95387
Total Acres
84.5
Parcel #
016-010-014
State Highways
SR 33
Railways
UPRR
Airports
Flying Bull
Waterways
San Joaquin River, Tuolumne River
Township
4S
Range
7E
Base
MDBM
Other Location Info
Grayson

Notice of Determination

Approving Agency
West Stanislaus Irrigation District
Approving Agency Role
Lead Agency
Approved On
Final Environmental Document Available at
116 E. St., Westley, CA 95387

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
No