Phase 2A - Central Park Recycled Water Main Extension Project
2 Documents in Project
Download CSV
New Search
Print
Summary
- SCH Number
- 2017091066
- Lead Agency
- Castaic Lake Water Agency
- Document Title
- Phase 2A - Central Park Recycled Water Main Extension Project
- Document Type
- NOD - Notice of Determination
- Received
- Posted
- 12/18/2017
- Present Land Use
- residential 5, public & semi public
- Document Description
- The proposed project would utilize recycled water from the Santa Clarita Valley Sanitation District's Valenciea WRP to service existing customers within CLWA's service area. The proposed project includes construction of up to 33,000 lf of new 24 in diameter pipeline and 16, and 12-in transmission pipeline and a reservoir within a 0.5-acre pad for storage of recycled water. The proposed project would convey an average annual demand of up to 560 acre-feet of recycled water from the Valencia WRP to customers along Newhall Ranch Rd and ultimately to Central Park.
- Contact Information
-
Rick Viergutz
Castaic Lake Water Agency
27234 Bouquet Canyon Road
Santa Clarita, CA 91350
Phone : (661) 513-1281
Location
- Coordinates
- 34°25'37.5"N 118°32'14.5"W
- Cities
- Santa Clarita
- Counties
- Los Angeles
- Cross Streets
- The Old Road, Newhall Ranch Rd, Rye Canyon Rd, Bouquet Canyon
- Zip
- 91350
- Total Acres
- 33,000lf; .5 ac
- State Highways
- I-5
- Schools
- Embiem ES
- Waterways
- Santa Clara River
- Township
- 4N
- Range
- 16W
- Base
- SB
Notice of Determination
- Approving Agency
- Castaic Lake Water Agency
- Approving Agency Role
- Lead Agency
- Approved On
- Final Environmental Document Available at
- 27234 Bouquet Canyon Road, Santa Clarita, CA 91350
Determinations
- (1) The project will have a significant impact on the environment
- No
- (2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
- No
- (2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
- Yes
- (2c) An other document type was prepared for this project pursuant to the provisions of CEQA
- No
- (3) Mitigated measures were made a condition of the approval of the project
- Yes
- (4) A mitigation reporting or monitoring plan was adopted for this project
- N/A
- (5) A Statement of Overriding Considerations was adopted for this project
- No
- (6) Findings were made pursuant to the provisions of CEQA
- Yes
Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613.