Burney Water District Wastewater Collection and Treatment Improvement Project

4 Documents in Project

Summary

SCH Number
2017082041
Lead Agency
Burney Water District
Document Title
Burney Water District Wastewater Collection and Treatment Improvement Project
Document Type
NOD - Notice of Determination
Received
Posted
9/22/2017
Present Land Use
wastewater treatment plant: GP & Z: Public fac; Use: Public wastewater treatment plant collection system: GP & Z: Various; use: PF located within public utility easements and on BWD-owned property.
Document Description
The proposed project entails sewer system improvements in the unincorporated community of Burney, including improvements to the existing wastewater treatment plant, Main Lift Station, and Bartel Lift Station; repair of approx four manholes; replacement of approx 1,700 lf of damaged pipeline; and repair of approx 40 pipeline mechanical deficiencies to eliminate cracked pipe, offset joints, etc.

Contact Information

Name
Willie Rodriguez
Agency Name
Burney Water District
Contact Types
Lead/Public Agency

Location

Counties
Shasta
Cross Streets
WWTP: Black Ranch Rd; Collection system:various
Zip
96013
Parcel #
030-390-015, 028, 034
State Highways
299
Schools
Burney ES/HS, Mt Burney Special Ed Center, Mountain View HS, Bur
Waterways
Burney Creek, Greer-Cornaz Ditch
Township
35N
Range
3E
Section
9,17,1
Base
MDM
Other Location Info
Burney

Notice of Determination

Approving Agency
Burney Water District Board of Directors
Approving Agency Role
Lead Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
Yes

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above.

Download CSV New Search Print