Infiltration Gallery Testing Project

5 Documents in Project

Summary

SCH Number
2017082019
Lead Agency
Stanislaus Regional Water Authority (SRWA)
Document Title
Infiltration Gallery Testing Project
Document Type
NOD - Notice of Determination
Received
Posted
9/29/2017
Present Land Use
agriculture, TID Infiltration gallery, Fox Grove Regional Park/A-2-40/Ag
Document Description
SRWA proposes to test the condition and operation of TID's existing infiltration gallery, construct a wet well, and install temporary pumping facilities to ascertain if it is feasible to proceed with the Surface Water Supply Project, a separate water supply project being considered by SRWA. The proposed project would include excavation of an area to access the infiltration gallery pipes; construction of a wet well and associated facilities adjacent to and connecting with the existing infiltration gallery; air purging and test pumping of the gallery pipes to dislodge sediment; pumping of river water through the gallery and into settling basins to inspect and test infiltration gallery and pump capacity and water quality; and disposal of the water, once any entrained sediment has settled out.

Contact Information

Name
Michael Brinton
Agency Name
Stanislaus Regional Water Authority
Contact Types
Lead/Public Agency

Location

Cities
Hughson
Counties
Stanislaus
Cross Streets
Geer Rd at Tuolumne River, river mile 26
Total Acres
~6
Parcel #
018-003-006, 018-004-012, 013, etc.
Railways
BNSF
Waterways
Tuolumne River

Notice of Determination

Approving Agency
Stanislaus Regional Water Authority
Approving Agency Role
Lead Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
No

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613.

Download CSV New Search Print