Salinas Avenue Culvert Replacement Project
2 Documents in Project
Download CSV
New Search
Print
Summary
- SCH Number
- 2017081023
- Lead Agency
- San Luis Obispo County
- Document Title
- Salinas Avenue Culvert Replacement Project
- Document Type
- NOD - Notice of Determination
- Received
- Posted
- 12/1/2017
- Present Land Use
- residential single-family (ROW)
- Document Description
- The San Luis Obispo County Public Works Department proposes to replace the existing culvert crossings with two 66-inch culverts and an associated private driveway culvert to satisfy County standards and increase the capacity of the crossing. Project implementation will improve public safety and access, reduce the need for road closures and maintenance resulting from flooding at this location. All work, including staging, will occur within the existing County right-of-way and will be located along the same alignment. Construction is expected to take two to three weeks to complete and will take place during the dry season.
- Contact Information
-
Kristie Scarazzo
San Luis Obispo County
County Government Center, Room 206
San Luis Obispo, CA 93408-2040
Phone : (805) 781-4263
Location
- Coordinates
- 35°33'04.5"N 120°30'26.8"W
- Counties
- San Luis Obispo
- Cross Streets
- Salinas Ave and Eddy St
- Zip
- 93465
- Total Acres
- 0.09
- State Highways
- 166, 101
- Schools
- Nipomo ES/HS
- Waterways
- Toad Creek
- Township
- 27E
- Range
- 29
- Section
- 12E
- Base
- MD
- Other Location Info
- Templeton
Notice of Determination
- Approving Agency
- San Luis Obispo County Board of Supervisors
- Approving Agency Role
- Lead Agency
- Approved On
- Final Environmental Document Available at
- SLO Co Public Works County Government Center Room 206, San Luis Obispo, CA 93408
Determinations
- (1) The project will have a significant impact on the environment
- No
- (2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
- No
- (2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
- No
- (2c) An other document type was prepared for this project pursuant to the provisions of CEQA
- No
- (3) Mitigated measures were made a condition of the approval of the project
- Yes
- (4) A mitigation reporting or monitoring plan was adopted for this project
- N/A
- (5) A Statement of Overriding Considerations was adopted for this project
- No
- (6) Findings were made pursuant to the provisions of CEQA
- Yes
Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613.