Holman Road Bridge at Bear Creek (Streambed Alteration Agreement No. 1600-2020-0058- R2)
11 Documents in Project
Summary
SCH Number
2017052062
Lead Agency
City of Stockton
Document Title
Holman Road Bridge at Bear Creek (Streambed Alteration Agreement No. 1600-2020-0058- R2)
Document Type
NOD - Notice of Determination
Received
Posted
5/14/2020
Document Description
limited to building of a new bridge crossing over Bear Creek for the northern Holman Road extension to Eight Mile Road. The bridge will accommodate four vehicular lanes (two in each direction), sidewalks, and a barrier-separated pathway. The proposed bridge will be approximately 210 feet long, and 83 feet wide. Abutments will be constructed at the top of the levees and will consist of a single row of 36-inch
diameter cast-in-drilled hole (CIDH) piles. There will be 10 piles at each abutment in the single row. The piers will have 16 piles for a total of 32 piles per pier. None of the piers or pilings will be constructed within the ordinary high-water mark or low flow channel of Bear Creek. The concrete lining will extend at least 20 feet
beyond the upstream and downstream ends of the piers.
Contact Information
Name
Amy Kennedy
Agency Name
California Department of Fish and Wildlife
Contact Types
Lead/Public Agency
Phone
Name
Agency Name
Matt Arnaiz, Holman Investors, LLC
Contact Types
Project Applicant
Location
Counties
San Joaquin
Regions
Northern California
Cross Streets
SR 99 and Eight Mile Road
State Highways
SR 99
Other Location Info
The bride will cross Bear Creek approximately 0.25 miles
north of the terminus of Holman Road.
Notice of Determination
Approving Agency
California Department of Fish and Wildlife
Approving Agency Role
Responsible Agency
Approved On
Determinations
(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
No
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
No
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
Yes
Attachments
Notice of Determination
Disclaimer: The Governor’s Office of Planning and Research (OPR) accepts no responsibility for the content or accessibility of these documents. To obtain an attachment in a different format, please contact the lead agency at the contact information listed above. For more information, please visit OPR’s Accessibility Site.