Ord Mountain Solar and Energy Storage Project

2 Documents in Project

Summary

SCH Number
2017051082
Lead Agency
San Bernardino County
Document Title
Ord Mountain Solar and Energy Storage Project
Document Type
NOP - Notice of Preparation of a Draft EIR
Received
Present Land Use
LV/AG, LV/AG-40
Document Description
Ord Mountain Solar, LLC proposes a CUP to construct and operate a solar energy generation and storage project on approx 484 acres to produce approx 160,000 megawatt-hours of renewable energy annually. The project would be a 60-MW alternating current PV solar energy facility with associated on-site substation, inverters, fencing, roads, and supervisory control and data acquisition system. The project would include a 60 MW AC max capacity, 4-hr energy storage battery system, and a 220-kilovolt overhead power line, referred to as a generation tie line, which would extend approx 0.6 mile southwest to SCE's proposed Calcite Substation. The project includes a major variance to modify the max structure height to 94 ft.

Contact Information

Name
John Oquendo
Agency Name
San Bernardino County
Contact Types
Lead/Public Agency

Location

Counties
San Bernardino
Cross Streets
SR 247, Fern Rd and Haynes Rd
Zip
92356
Total Acres
484
Parcel #
0453-041-07, -091-11, -12, -24, etc
State Highways
SR 247
Township
6N
Range
1W
Section
36
Other Location Info
Lucerne Valley

Notice of Completion

State Review Period Start
State Review Period End
State Reviewing Agencies
Air Resources Board, Major Industrial Projects, California Department of Parks and Recreation, California Department of Transportation, District 8 (DOT), California Energy Commission, California Highway Patrol, California Public Utilities Commission (CPUC), California Regional Water Quality Control Board, Lahontan Victorville Region 6 (RWQCB), Department of Fish and Wildlife, Region 6, Department of Water Resources, Resources Agency, California Native American Heritage Commission (NAHC)
State Reviewing Agency Comments
California Native American Heritage Commission (NAHC)
Development Types
Power:Solar (Megawatts 60)
Local Actions
Use Permit
Project Issues
Aesthetics, Air Quality, Biological Resources, Geology/Soils, Hazards & Hazardous Materials, Hydrology/Water Quality, Land Use/Planning, Noise, Public Services, Transportation

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613.

Download CSV New Search Print