GWMA Recycled Water Pipelines Project in the City of Bell Gardens

4 Documents in Project

Summary

SCH Number
2017051048
Lead Agency
Central Basin Municipal Water District
Document Title
GWMA Recycled Water Pipelines Project in the City of Bell Gardens
Document Type
NOD - Notice of Determination
Received

Document Description
Project would include the installation of approx. 5,835 lineal feet of recycled water pipeline varying in diameter from 8 to 16 inches. The proposed recycled water pipeline would connect to Central Basin's 16-inch diameter recycled water pipeline in Garfield Ave. at its intersection with Park Lane. The pipeline would be installed in Garfield Avenue in a northerly direction to its intersection with Florence Place the pipeline would be reduced in diameter to 12 inches. Approx. 2,600 lineal feet of 12-inch diameter pipeline would be installed in an easterly direction in Florence Place to its intersection with Sudan Avenue. Approx. 230 lineal feet of 8-inch diameter recycled water pipeline would also be installed in Emil Avenue in a northerly direction from Florence Place. The new recycled water pipeline would serve Veterans Park and Suva Elementary/Middle School Complex.

Contact Information
Keith S. Dunbar
Central Basin Municipal Water District
45375 Vista Del Mar
Temecula, CA 92590-4314

951-699-2082
ksdpe67@gmail.com

Location

Coordinates
33°57'59"N 118°09'04"W
Cities
Bell Gardens
Counties
Los Angeles
Cross Streets
Garfield Ave and Florence Place
Zip
90201
State Highways
5, 710
Schools
Suva School Complex
Waterways
Rio Hondo
Base
SBBM

Notice of Determination

Approving Agency
Board of Directors, Central Basin Municipal WAter District
Approving Agency Role
Lead Agency
Approved On
Final EIR Available Location
6242 Telegraph Road, Commerce, CA 90040-2512

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A Statement of Overriding Considerations was adopted for this project
No
(5) Findings were made pursuant to the provisions of CEQA
No