16-CUP-06 Battery Energy Storage System

2 Documents in Project

Summary

SCH Number
2017051036
Lead Agency
Santa Paula, City of (City of Santa Paula)
Document Title
16-CUP-06 Battery Energy Storage System
Document Type
NOD - Notice of Determination
Received

Document Description
Construction and operation of a battery electrical storage system that would store up to MW of electricity for dispatch into the local Southern CA Edison grid via the existing adjacent Wakefield Substation. The storage system would consist of 20 self-contained battery storage modules that would each house mounting battery racks, 22 lithium-ion battery cells, and associated electrical equipment. The battery storage modules would be made from converted shipping containers. The storage modules would be surrounded by an access drive aisle. An overhead solar panel array would be containers. The storage modules would be surrounded by an access drive aisle. An overhead solar panel array would be constructed across the top of the modules to charge the batteries. The entire project site would be fenced for security and restricted access. An existing office building on the site would be renovated and used as an office by the project applicant.

Contact Information
Janna Minsk
City of Santa Paula
970 Ventura Street
Santa Paula, CA 93060

(805) 933-4214

Location

Coordinates
34°21'24.4"N 119°3'18"W
Cities
Santa Paula
Counties
Ventura
Cross Streets
North 13th St & East Main St
Zip
93060
Total Acres
1.53
Parcel #
101-0-241-185
State Highways
150, 126
Railways
yes
Airports
Santa Paula
Schools
Yes
Waterways
Santa Clara River, Santa Paula Creek

Notice of Determination

Approving Agency
City of Santa Paula
Approving Agency Role
Lead Agency
Approved On
Final EIR Available Location
970 Ventura St., Santa Paula, CA 93060

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A Statement of Overriding Considerations was adopted for this project
N/A
(5) Findings were made pursuant to the provisions of CEQA
Yes