South of Palermo 115 kV Power Line Reinforcement Project (California Endangered Species Act Incidental Take Permit No. 2081-2017-020-02 (ITP))

11 Documents in Project

Summary

SCH Number
2017042051
Lead Agency
California Public Utilities Commission (CPUC)
Document Title
South of Palermo 115 kV Power Line Reinforcement Project (California Endangered Species Act Incidental Take Permit No. 2081-2017-020-02 (ITP))
Document Type
NOD - Notice of Determination
Received
Posted
7/20/2018
Present Land Use
LU: gen ag, exclusive ag, ag/res, res, light industrial, and gen commercial uses
Document Description
This proposed project involves replacing existing transmission wires (reconductoring) and modifying or replacing existing lattice steel structures along approx. 59.5 miles of the existing Palermo-Rio Oso 115 kV transmission system alignment. The Project will take place along five segments of the existing transmission line: South of Palermo Line (approx. 38.7 miles), Palermo Sub Line Segment (Approx. 1.6 miles), Pease Sub Line Segment (approx. 5.2 miles), Bogue Sub Line Segment (approx. 6.4 miles), and Rio Oso Sub Line Segment Loop (approx. 7.6 miles). Project will result in temporary impacts to 22.119 acres of giant garter snake (Thamnophis gigas) habitat and the permanently remove 0.085 acres of habitat. The project is expected to result in incidental take of giant garter snake, which is designated as a threatened species under the CESA. The ITP referenced above as issued by CDFW authorizes incidental take of species listed under CESA that may occur as a result of Project implementation.

Contact Information

Name
Patrick Moeszinger
Agency Name
CDFW
Contact Types
Lead/Public Agency

Location

Cities
Marysville, Yuba City
Counties
Butte, Sutter, Yuba
Cross Streets
SR 70
Zip
95968,9590
State Highways
70
Township
12N
Range
4E
Section
21
Base
MD

Notice of Determination

Approving Agency
CDFW
Approving Agency Role
Responsible Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA