Environmental Cleanup of IR-6 and IR-8 Drainages (Lake or Streambed Alteration Agreement No. 1600-2017-0040-R3)

3 Documents in Project

Summary

SCH Number
2017042029
Lead Agency
Regional Water Quality Control Board, Region 2 (San Francisco Bay), Oakland
Document Title
Environmental Cleanup of IR-6 and IR-8 Drainages (Lake or Streambed Alteration Agreement No. 1600-2017-0040-R3)
Document Type
NOD - Notice of Determination
Received
Posted
7/3/2017
Present Land Use
Institutional / General Open Space / Future Study; Zoned R-E/S-11 (Residential Estates with a 1- to 5-acre minimum lot size)
Document Description
CDFW has executed Lake and Streambed Alteration Agreement No. 1600-2017-0040-R3, pursuant to section 1602 of the Fish and Game Code to the Project Applicant, SLAC National Accelerator Laboratory. Project is limited to removal of PCB-contaminated soil within wetland and riparian areas. The excavations will affect approx. 0.23 acres of intermittent and perennial channel habitat, including marsh wetlands. Approx. 0.67 acres of riparian vegetation will also be impacted. After removal of contaminated soils, clean, imported granular fill will be added to the channel to restore pre-construction channel geomorphology. In areas currently lined with riprap, the riprap will be removed and replaced after cleaning. Disturbed areas will be replanted after construction with locally collected willow stakes and cattails.

Contact Information

Name
Randi Adair
Agency Name
CDFW
Contact Types
Lead/Public Agency

Location

Cities
Menlo Park
Counties
San Mateo
Cross Streets
Sand Hill Road, I-280
Zip
94025
Total Acres
3.91
Parcel #
074-480-230, -200, -370, -340
State Highways
I-280
Township
6S
Range
3W
Section
16

Notice of Determination

Approving Agency
CDFW
Approving Agency Role
Responsible Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
N/A
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
No

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613.