Environmental Cleanup of IR-6 and IR-8 Drainage Channels
3 Documents in Project
Download CSV
New Search
Print
Summary
- SCH Number
- 2017042029
- Lead Agency
- Regional Water Quality Control Board, Region 2 (San Francisco Bay), Oakland
- Document Title
- Environmental Cleanup of IR-6 and IR-8 Drainage Channels
- Document Type
- NOD - Notice of Determination
- Received
- Posted
- 6/9/2017
- Present Land Use
- Institutional / General Open Space / Future Study; Zoned R-E/S-11 (Residential Estates with a 1- to 5-acre minimum lot size)
- Document Description
- The project is intended to be a final action to remove soil containing polychlorinated biphenyls (PCBs) from portions of three earthen drainage channels at SLAC to address cleanup requirements of Water Board Cleanup and Abatement Order R2-2009-0072. Approx. 1,550 bank cubic yards of soil will be removed in the course of excavation. Following soil removal, the drainages will be backfilled and restored.
- Contact Information
-
Nathan King
Regional Water Quality Control Board, Region 2 (San Francisco Ba
1515 Clay Street, Suite 1400
Oakland, CA 94612
Phone : (510) 622-3966
Location
- Coordinates
- 37°24'48.9"N 122°11'59.5"W
- Cities
- Menlo Park
- Counties
- San Mateo
- Cross Streets
- Sand Hill Road, I-280
- Zip
- 94025
- Total Acres
- 3.91
- Parcel #
- 074-480-230, -200, -370, -340
- State Highways
- I-280
- Township
- 6S
- Range
- 3W
- Section
- 16
Notice of Determination
- Approving Agency
- SF Bay Regional Water Quality Control Board
- Approving Agency Role
- Lead Agency
- Approved On
- Final Environmental Document Available at
- 1515 Clay St., 14th Floor, Oakland, CA 94612
Determinations
- (1) The project will have a significant impact on the environment
- No
- (2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
- No
- (2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
- Yes
- (2c) An other document type was prepared for this project pursuant to the provisions of CEQA
- No
- (3) Mitigated measures were made a condition of the approval of the project
- Yes
- (4) A mitigation reporting or monitoring plan was adopted for this project
- N/A
- (5) A Statement of Overriding Considerations was adopted for this project
- No
- (6) Findings were made pursuant to the provisions of CEQA
- N/A
Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613.