Santa Ysabel Nature Center
2 Documents in Project
Summary
SCH Number
2017031019
Lead Agency
San Diego County
Document Title
Santa Ysabel Nature Center
Document Type
NOD - Notice of Determination
Received
Posted
5/10/2017
Present Land Use
grazing/zoned S80/Regional land use element policy and GP 2805
Document Description
The project consists of the development of 6.55 acres for a Nature Center including the interpretive center building, a parking lot, a maintenance facility/volunteer pad (a concrete pad with room for a motor home and a patio) complex, and appurtenant outdoor facilities such as demonstration gardens, trails, and the like. The interpretive center building will consist of a combination of the following types of uses: office space, exhibit area, conference/banquet area, bathrooms, a lobby/entry plaza, and/or a covered patio. The site contains an existing groundwater well that would be retained. Permits from Caltrans would be obtained to access the site by a private road/driveway from highway 79. The project would be served by on site septic systems and groundwater from outside any water municipal district. Approx 1,000 ft of extension of sewer or water utilities may be required by the project. The following project design considerations are also being implemented to minimize environmental impacts: (1) no drainages will be impacted by the project and all crossings will be made by pedestrian bridge, (2) impacts tot eh open Engelmann oak (Quercus engelmannii) woodland root protection zone will be minimized and there will be no net loss of oak trees by implementing the project, (3) all historical and archaeological sites will be fenced off by a qualified archaeologist prior to construction and therefore be protected from incurring significant impacts.
Contact Information
Name
Deborah Mosley
Agency Name
San Diego County
Contact Types
Lead/Public Agency
Phone
Location
Coordinates
Counties
San Diego
Cross Streets
CA Highway 78 and 79
Zip
92070
Total Acres
84.3
Parcel #
2471601400
State Highways
79, 79
Schools
Spencer Valley ES
Waterways
Santa Ysabel Creek
Township
12S
Range
3E
Section
21
Other Location Info
Santa Ysabel
Notice of Determination
Approving Agency
San Diego County Board of Supervsiors
Approving Agency Role
Lead Agency
Approved On
Determinations
(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
N/A
(6) Findings were made pursuant to the provisions of CEQA
N/A
Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above.