San Pablo Clearwell Replacement and Water Treatment Plant Rehabilitation Project

2 Documents in Project

Summary

SCH Number
2017028190
Public Agency
East Bay Municipal Utility District (EBMUD)
Document Title
San Pablo Clearwell Replacement and Water Treatment Plant Rehabilitation Project
Document Type
NOE - Notice of Exemption
Received
Posted
10/11/2017
Document Description
Demolition of the existing 5.4-million gallon San Pablo Clearwell open cut reservoir followed by construction of two 3.5 MG replacement concrete tanks within the basin of the existing clearwell, installation of approx. 1,250 feet of onsite and offsite transmission pipelines , and rehabilitation work at the San Pablo Water Treatment Plant.

Contact Information

Name
Jennifer L. McGregor
Agency Name
East Bay Municipal Utility District
Contact Types
Lead/Public Agency

Location

Counties
Contra Costa
Cross Streets
300 Berkeley Park Blvd
Other Location Info
Kensington
Other Information
300 Berkeley Park Boulevard

Notice of Exemption

Exempt Status
Categorical Exemption
Type, Section or Code
S:15301(d),15302(c),15282(k)
Reasons for Exemption
Project will be conducted in previously disturbed/developed areas. the project is exempt, because it entails the preplacement of an existing utility system, facilities involving negligible expansion of capacity, and installation of a new pipeline less than one mile in length.

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613.