Recycled WAter Improvements at WWTF (Project); Clean Water State Revolving Fund (CWSRF) No. C-06-8093-210

3 Documents in Project

Summary

SCH Number
2017021040
Lead Agency
City of Huron
Document Title
Recycled WAter Improvements at WWTF (Project); Clean Water State Revolving Fund (CWSRF) No. C-06-8093-210
Document Type
NOD - Notice of Determination
Received
Posted
4/5/2018
Present Land Use
existing WWTP and vacant ag designated lands
Document Description
The City prepared a Recycled Water Feasibility Study to comply with the Central Valley Regional Water Quality Control Board Waste Discharge Requirements Order No. R5-2014-0163. The City has determined that recycling treated effluent on newly developed agricultural land adjacent to the Wastewater Treatment Plant (WWTP) is the most beneficial use for their treated effluent. Effluent will be applied to the reclamation area during periods when alfalfa is being grown/harvested. When effluent is not needed for the crops or otherwise is not discharged to the reclamation area, it will continue to be stored in the lined storage ponds. The City will also incorporate certain improvements and rehabilitation measures to improve the operation of the existing WWTP. Such improvements include rehabilitating the plant's headworks, replacing aerators in the treatment ponds, determining feasible way to clean out the aeration treatment ponds, lining the percolation/evaporation ponds, adding an emergency storage pond and pump station to recirculate water back to the treatment ponds.

Contact Information

Name
Sahil Pathak
Agency Name
SWRCB
Contact Types
Lead/Public Agency

Location

Cities
Huron
Counties
Fresno
Cross Streets
Palmer Ave between Siskiyou Ave and Madera Ave
Zip
93234
Total Acres
200
Parcel #
075-032-18T, 19ST, 22 ST
Schools
Chestnut HS
Waterways
Los Gatos Creek
Township
20S
Range
17E
Section
1
Base
MDBM

Notice of Determination

Approving Agency
State Water Board
Approving Agency Role
Responsible Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
N/A

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613.

Download CSV New Search Print