Sanger Substation Expansion Project

3 Documents in Project

Summary

SCH Number
2017012039
Lead Agency
Public Utilities Commission (California Public Utilities Commission)
Document Title
Sanger Substation Expansion Project
Document Type
NOD - Notice of Determination
Received

Document Description
The Sanger Substation Expansion Project would be located in unincorporated Fresno County, at the northwest corner of the intersection of East Jensen Avenue and South McCall Ave. The project would include a 7-acre expansion north of the existing Sanger Substation, equipment removal, power line reconfiguration, changes to the existing Sanger Substation, and Installation of two antenna dishes on an existing microwave tower at the Fence Meadow Repeater Station. The project is integral to the Central Valley 115 kV transmission system, providing service to a critical energy path between Fresno metropolitan north and south areas.

Contact Information
Billie Blanchard
California Public Utilities Commission
505 Van Ness Avenue
San Francisco, CA 94102-3298

(415) 703-2068

Location

Coordinates
36°42'24.27"N 119°36'37.36"W
Cities
Sanger
Counties
Fresno
Cross Streets
East Jensen Ave and South McCall Ave
Zip
93657
Total Acres
11.6
Parcel #
14002002T

Notice of Determination

Approving Agency
CA Public Utilities commission
Approving Agency Role
Lead Agency
Approved On
Final EIR Available Location
505 Van Ness Ave., 4th Floor, SF, CA 94102

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A Statement of Overriding Considerations was adopted for this project
No
(5) Findings were made pursuant to the provisions of CEQA
No
Download CSV New Search