New Hollister School Removal Action Workplan

3 Documents in Project

Summary

SCH Number
2017011004
Lead Agency
Toxic Substance Control, Department of (Department of Toxic Substances Control)
Document Title
New Hollister School Removal Action Workplan
Document Type
NOD - Notice of Determination
Received

Document Description
The Department of Toxic Substances Control (DTSC) approved the Removal Action Workplan (RAW) for the New Hollister School Site. The cleanup decision document, referred to as the RAW, addressed naturally-occurring asbestos (NOA) concentrations in the soil at the 12-acre new elementary school site within the Santana Ranch Specific Plan area. The approved project activities consist of capping the surface of the Project Site with a combination of non-NOA caps, including a three-foot engineered soil cover, as Is proposed for the playfleld area (approximately 1/3 of the Site), a one to two-foot cap in landscaped areas, and using a variety of engineered caps across the remainder of the Site, including asphalt pavement, concrete flatwork, and building foundations and slabs. The soil cover cap areas would be underlain by a marker barrier indicating the presence of NOA containing soil beneath the marker. The cap would be used to minimize the potential for contact with· the contaminated soil. A total of approximately four acres of affected soil would need to be covered. The contaminated soil would be Included beneath the cap. *See NOD for full details.

Contact Information
Jose Luevano
DTSC
8800 Cal Center Drive
Sacramento, CA 95826

9162553577

Location

Cities
Hollister
Counties
San Benito
Other Location Info
Northeast corner of Fairview Road and Sunnyslope Road, Hollister, 95023

Notice of Determination

Approving Agency
DTSC
Approving Agency Role
Responsible Agency
Approved On
Final EIR Available Location
8800 Cal Center Drive Sacramento, CA 95826

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A Statement of Overriding Considerations was adopted for this project
No
(5) Findings were made pursuant to the provisions of CEQA
Yes